You are using an unsupported browser. Please update your browser to the latest version on or before July 31, 2020.
close
You are viewing the article in preview mode. It is not live at the moment.

Showing articles from framing tag

Structural Steel framing Connections

Evaluate with the steel fabricator how the structural engineer has designed the connections. It may save time on installation to change details calling for welds to all bolted and accelerate schedule/save on labor.

HVAC Equipment Structural Loads

Project Plan: Construction Delivery Method: EPC (Engineer Procure Construct) The weight of the HVAC units and LEF-1 central exhaust unit increased dramatically from 30% design level to IFC. Ultimately some additional steel reinforcing was required for supporting LEF-1 fans. This added cost to the project.

scroll to top icon