Electrical Room Door Swing

Project Phase: Construction/Installation Delivery Method: EPC (Engineer Procure Construct) Statement of Problem: After substantial completion, the Owner''s facility maintenance person questioned the door swing of the electrical room, which swings into the room. He cited that per building code, any electrical roo…

Hazardous Materials Requirements

Project Phase:Construction/Installation Delivery method: EPC (Engineer Procure Construct) Statement of problem: The DTE laboratory has a specialized coal prep room which contains coal processing equipment. The room was classified as H-2 occupancy with explosion relief wall and all electrical within the room is c…