Bus Shutdown
print icon
  Project Phase: Design
Delivery Method: General contract-Prime

Bus shut downs were not part of the master schedule. This caused a lot of heart ache with the plant as bus plug shutdowns affected other contractor''''s work. The owner did not want bus shutdowns within the master schedule due to anticipated changing dates. Also nobody (including Owner) knew the actual layout of the buses within the building.
Feedback
0 out of 0 found this helpful

Attachments

Lesson_Learned_-_Bus_Shutdowns.pdf