Orientation
print icon

Project Phase- Construction/Installation
Delivery Method- General Contract-Prime

CCC orientation was to follow the CM for Ford orientation at the Conference Center Hall. The Friday at approx 3:30 pm before the Mass orientations on Monday we were informed that Aristeo (CM for Ford) had to open more orientation spots and therefore we could not use those times to do our orientations. Plus the way the orientation was run by the CM meant people were filtering through in small groups with limited time to go through our orientation.