Zone Management
print icon
  Project Phase- Construction/Installation
Delivery Method- General Contract-Prime

CCC''s Supervision was scattered throughout the plant without defined responsibilities. Because of this, the customer would call the PM for any and all issues rather than the person responsible for that zone.
We had 1 punchlist / clean sweep binder for all zones, but each zone needed its own binder that would be used for both shifts.