Project Phase- Construction/Installation Delivery Method- General Contract-Prime Make sure that environmental subcontractor understands what the scope of work is and that they patrol the areas themselves instead of CCC running their crews. The environmental sub (AMS) did not fully understand the scope of the job and so they were falling behind schedule. |